Doosan Equipment Machine Relief Pressure Check Guide

Doosan equipment machine relief pressure check guide,it must be performed for VBO calibration.

 

Preparations:

Doosan Data Monitoring System DMS-5 DMS-3 Free Download

Doosan Diagnostic Tool

 

Relief pressure check

*Calibration judgement

Doosan Equipment Machine Relief Pressure Check Guide (1)

5.1. Measure the input & output voltage of main pump pressure sensor

5.1.1. Check the output voltage when it is connected under unloaded condition.

5.1.2. Check the output voltage of the pilot pressure sensor while the machine is in operation.

(Take the DMS-5 monitoring data during the test)

5.1.3. Check if the voltage value measured at the pressure sensor is matched with the pressure indicated on the gauge panel.

5.1.4. Operate the machine and check if the pressure value indicated on the gauge panel is changed according to changes in the pressure.

Ex. DX350LC-7(Please refer the shop manual to check the exact value on each model)

*Operating voltage: 5V ± 5%, Output voltage: 1 ~ 5V, Operating current: max. 10 mA, measuring pressure: 0 to 500 bar, Measurement tolerance: ±5%

*Formula for voltage-pressure conversion: Voltage = (0.00816 x Pressure) + 1

5.2. Check the physical condition of the main pump pressure sensor

5.2.1. Assembly condition

5.2.2. External damage

5.2.3. Short circuit

Ex. DX350LC-7(Please refer the shop manual to check the exact value on each model)

Doosan Equipment Machine Relief Pressure Check Guide (2)

5.3. Check the physical condition of the main relief valve on MCV

5.3.1. Assembly condition

5.3.2. Internal blockage

Doosan Equipment Machine Relief Pressure Check Guide (3)

 

More topics for Doosan,please refer to:Doosan Trouble Repair

Visited 1 times, 1 visit(s) today