The UseCase SCR-EOL is oppened from UseCase “SCR-Overview”
by pressing

 

 

Test is running as follows:
Step 1
– Start with click to

During whole test a stop is possible with activate

In order to run the test correct, following preferences have to be fulfilled:

Note:

No active error in ECU!
Engine speed is higher than 1500 rpm!
The used engine torque is more than 50% of the available torque!
If one of these three conditions is not met for more than 5 seconds,
the test is automatically aborted.

 

Step 2 – Trigger: temperatur prior oxi-catalyst >= 180°C
After step 1 is over, temerature is >180°C and all start conditions are met,a timer starts counting for 20 seconds (you can follow the timer, viewing the progress bar below the status window).

 

If the pressure of the SCR-pump will not reach more than 8,5 bar within the timer is running, the test will stop.
Deutz Communicator

 

 

Step 3 – Trigger: temperatur prior oxi-catalyst >= 250°C
After step 2 is finished successfully and temperature is more than 250°C ,a timer starts counting for 5 minutes (you can follow the timer, viewing the progress bar below the status window)

 

Test will stop, if AdBlue injection mass ist still lower than 10mg or NOX-value (prior catalyst) is higher than 10ppm within 5 minutes testing time.

Step 4 –Trigger: AdBlue amount >10mg, NOX-value (prior CAT) > 10ppm
For 10sec. an averaging of NOX values prior and after oxidation catalyst takes place.
The decrease of NOX concentration is measured meanwhile by collecting the min- and max-values of NOX concentration.
If, while averaging process takes place, the concentration gradient > 50ppm/10sec, averaging will stop and start again (in order to guarantee a
stationary measuring point).
After 5 repetitions without reaching a stationary operating point,the test is stopped completely.
Test is successful if converting rate is higher than 30%.
The test result is shown in an overview screen :

The result can be saved in a Log-file:

 

More topic for Deutz,please refer to Deutz Trouble Repair

auto

Recent Posts

How to Solve JCB SPN 102, FMI 1 Boost Pressure Sensor: Pressure Below Normal

Here is the instruction show you guide on how to JCB machine SPN 102,FMI 1…

2 days ago

How to Install Preconcave for CLAAS Lexion 480 Combine

This instruction show you guide on how to install preconcave for CLAAS Lexion 480 combine…

4 days ago

Deutz EMR3 Trouble Code 78/ 190 Speed Sensor Signals Out of Phase

This instruction show you guide on how to solve Deutz EMR3 trouble code 78/ 190 EngMOfsCaSCrS Speed…

1 week ago

How to Release Park Brake Manually for CASE IH 20 Series Combine

This instruction show you guide on how to release park brake manually for CASE IH…

1 week ago

How to Replace High Pressure Limit Valve for Fendt 900 Vario COM III?

Here is the instruction show you guide on how to replace high pressure limit valve…

2 weeks ago

How to Select JCB Machine AJ45E Machine Software

There are three software options for Machine Software on AJ45E&EH machines.   Related Contents: 2025 JCB…

2 weeks ago