Perkins 400A/400D Engine Exhaust Manifold Removal and Installation Guide

This instruction show you guide on how to remove and install exhaust manifold for Perkins 400A and 400D industrial engines.

 

Related Contents:

Perkins EST 2024A & 2023A & 2019A Software Free Download

Perkins SPI2 2018A EPC+Service Manual Free Download

 

Procedures:

Removal Procedure
Start By:
a.If the engine is equipped with a turbocharger,remove the turbocharger. Refer to Disassembly and Assembly, “Turbocharger,Remove and Install”.

NOTICE
Keep all parts clean from contaminants.
Contaminants may cause rapid wear and shortened component life.
Note: The two cylinder, the three cylinder and the four cylinder engines have different exhaust
manifolds. The removal procedure is similar for all models.Illustration 25 g01326567

1.Loosen nuts (5) and bolts (6).
Note: To prevent distortion of the exhaust manifold,loosen the outer fasteners first.
2.Remove nuts (5) and bolts (6).
Note: Identify bolts of different lengths so that the bolts can be installed in the correct positions.
3.Remove exhaust manifold (4) from cylinder head
(1 Note the orientation of the exhaust manifold for installation.
4.Remove gasket (3) from cylinder head (1).
5.If necessary, remove exhaust manifold studs (2) from cylinder head (1).

Installation Procedure
NOTICE
Keep all parts clean from contaminants.
Contaminants may cause rapid wear and shortened component life.
Note: The two cylinder, the three cylinder and the four cylinder engines have different exhaust manifolds. The installation procedure is similar for all models.

1.Ensure that the mating surfaces of the cylinder head and the exhaust manifold are clean and free from damage.

2.If necessary, install exhaust manifold studs (2) to cylinder head (1).
3.Install a new exhaust manifold gasket (3) to cylinder head (1).
4.Align exhaust manifold (4) with studs (2) and install the exhaust manifold to cylinder head (1).
Note: Ensure that the exhaust manifold is installed in the correct orientation.
5.Install nuts (5) and bolts (6) finger tight.
Note: Ensure that bolts of different lengths are installed in the correct positions.

6.For 402D-05, 403D-07, 403A-11, 403D-11, 403A-15, 403D-15, 403D-15T, 403D-17, and 404D-15 engines, tighten nuts (5) and bolts (6) to a torque of 10 N·m (89 lb in).
For 404A-22, 404D-22, 404D-22T, and 404D-22TA engines, tighten nuts (5) and bolts (6) to a torque of 25 N·m (18 lb ft).
Note: On three cylinder engines and four cylinder engines, tighten the inner bolts first.
End By:
a.If the engine is equipped with a turbocharger,install the turbocharger. Refer to Disassembly and Assembly, “Turbocharger, Remove and Install”.

More Perkins case,please refer to:Perkins Engine Trouble Repair

auto

Recent Posts

HITACHI Construction 4JJ1 P0092 Fuel Pressure Regulator Control Circuit High

Here car-auto-repair.com show you guide on how to solve ISUZU construction 4JJ1 engine P0092 fuel…

1 day ago

How to Solve Perkins 1106D EPG Engine E398 Low Fuel Rail Pressure Error

Here is the illustration show you guide on how to solve Perkins 1106D electric power…

2 days ago

Deutz EMR3 Aassembly Inspection and Initialisation Test Guide

Here comes the instruction on how to use SerDia2010 to perform assembly inspection and initialization…

3 days ago

HITACHI ZX-5 Excavator No Load Max Differential Pressure Measurement Guide

This instruction show you guide on how to perform No load max differential pressure measurement…

4 days ago

How to Solve Doosan Machine P02EB Over Temperature Error

Here is the instruction show you guide on how to solve Doosan machine P02EB over…

5 days ago

How to Perform Relative Cylinder Compression Test for Detroit GHG17 Engine

This illustration show you how to use Detroit Diesel Diagnostic Link diagnostic software to do…

6 days ago